D.E.1.1
Consortium Agreement and Meeting Calendar
|
E 1
|
31/08/2014
|
20/12/2014
|
DONE
|
ALL
|
|
D.D.3.1.
Notice Board ( beginning of the project)
|
D 3
|
30/09/2014
|
30/10/2014
|
DONE
|
AITEX
|
D_D_3_1 Notice Board_PHOTOCITYTEX-1.pdf |
D.D.2.1
Website of the project (September 2014.Maintenance all the
project)
|
D 2
|
30/09/2014
|
20/09/2014
|
DONE
|
CEAM
|
D_D_2_1_WEBPAGE.pdf |
D.D.2.2
Information about the project in each Partner website (September
2014. Maintenance all the project)
|
D 2
|
30/09/2014
|
10/01/2015
|
DONE
|
ALL
|
|
D.A.1.1.
Technical report: compilation of technical data sheets of
photoactive additives and building materials, not exclusively
products in textile format
|
A 1
|
31/10/2014
|
13/11/2014
|
DONE
|
NTT
AITEX
|
Confidential,
only for the members of the Consortium (including the Commission
Services) |
D.A.1.2.
Technical report: European air quality condition, concentration
of pollutants data (tables and graphs) and main
conclusions.
|
A 1
|
31/10/2014
|
15/11/2014
|
DONE
|
CEAM
LEGAMBIENTE
|
Confidential,
only for the members of the Consortium (including the Commission
Services) |
D.B.2.1.Technical
data sheet of photocatalytic textile structures to be implemented
in purifying polluted atmospheres
|
B 2
|
31/10/2014
|
07/01/2015
|
DONE
|
NTT
AITEX
|
Confidential,
only for the members of the Consortium (including the Commission
Services) |
D.B.1.1 First
results of the air measurement (Six months reports with the first
results of the air measurements (chemical speciation,
concentration profiles, etc.)
|
B 1
|
31/12/2014
|
15-03/2015
|
DONE
|
CEAM
|
|
D.E.2.1:
Database with some information of the main LIFE project which
have relation with thisproject (carried out during the project
andupdated continuously)
|
E 2
|
31/01/2015
|
15-03/2015
|
DONE
|
NTT
CEAM
|
|
D.B.2.2.
Technical report related to manufacture and characterization of
lab scale prototypes
|
B 2
|
28/02/2015
|
01/01/2015
|
DONE
|
AITEX
NTT
|
|
D.B.2.3.
Prototypes of photocatalytic textiles developed at lab
scale
|
B 2
|
28/02/2015
|
31/07/2015
|
DONE
|
AITEX
NTT
|
|
D.E.1.2
Inception Report (to be delivered within 9 months after the
project start)
|
E 1
|
31/03/2015
|
28/03/2015
|
DONE
|
CEAM
|
|
D.B.1.2 Final
results of the air measurement (Six months reports with the
updated results of the air measurements (chemical speciation,
concentration profiles, etc.)
|
B 1
|
30/06/2015
|
30/04/2016
|
DONE
|
CEAM
|
|
D.B.2.4.
Technical report related to manufacture and characterization of
semi-industrial scale prototypes
|
B 2
|
30/06/2015
|
01/04/2016
|
DONE
|
AITEX
NTT
|
|
D.B.2.5.
Prototypes of photocatalytic textiles developed at
semi-industrial scale
|
B 2
|
30/06/2015
|
15/04/2016
|
DONE
|
AITEX
NTT
|
|
D.D.1.1
Dissemination and Communication plan
|
D 1
|
31/10/2015
|
31/10/2015
|
DONE
|
AITEX
ALL PARTNERS
|
|
D.D.1.2
Newsletter and dissemination material
|
D 1
|
31/12/2015
|
31/12/2015
|
DONE
|
AITEX
ALL PARTNERS
|
|
D.B.3.1
Results report of 50% of photoactivity tests performed at
EUPHORE
|
B 3
|
29/02/2016
|
15/03/2016
|
DONE
|
CEAM
|
|
D.B.4.1. First
nine months results report of demonstration tests in urban
environments performed in Quart de Poblet
|
B 4
|
30/04/2016
|
31/03/2016
|
DONE
|
CEAM
|
|
D.D.1.4
Dissemination material: leaflet, roll up banner
|
D 1
|
30/04/2016
|
30/04/2016
|
DONE
|
AITEX
|
|
D.E.1.3 Mid
Term Report (covering the first 18 months)
|
E 1
|
30/04/2016
|
30/04/2016
|
DONE
|
CEAM
|
|
D.B.3.2.
Results report of 100 % of photoactivity tests performed at
EUPHORE
|
B 3
|
31/07/2016
|
31/05/2017
|
DONE
|
CEAM
|
|
D.D.1.3
Newsletter and dissemination material 2016
|
D 1
|
31/12/2016
|
21/12/2016
|
DONE
|
AITEX
|
|
D.D.1.5
Divulgation material (CD, pen drive or Agenda)
|
D 1
|
31/03/2017
|
30/06/2017
|
DONE
|
AITEX
CEAM
|
|
D. D. 3.1.
Notice Board ( results of the project)
|
D 3
|
30/04/2017
|
30/06/2017
|
DONE
|
AITEX
|
|
D.B.4.2. Final
results report of demonstration tests in urban environments
performed in Quart de Poblet
|
B 4
|
30/04/2017
|
30/06/2017
|
DONE
|
CEAM
|
|
D.B.4.3.
Technical protocol of use of photoactive textiles for the
decontamination of urban environments
|
B 4
|
30/04/2017
|
30/06/2017
|
DONE
|
CEAM
|
|
D.D.4.1
Layman's Report
|
D 4
|
29/06/2017
|
30/06/2017
|
DONE
|
ALL
|
|
D.C.1.1
Environmental Impact Report
|
C 1
|
30/06/2017
|
31/05/2017
|
DONE
|
CEAM
|
|
D.C.1.2 Simple
mathematic model
|
C 1
|
30/06/2017
|
30/06/2017
|
DONE
|
AITEX
CEAM
|
|
D.C.2.1.Socio-Economic
Impact Report
|
C 2
|
30/06/2017
|
30/06/2017
|
DONE
|
LEGAMBIENTE
NTT
|
|
D.E.1.4 Final
Report (covering the whole project)
|
E 1
|
30/06/2017
|
30/06/2017
|
DONE
|
CEAM/ALL
|
|
D.E.2.2:
Report of the Final Event and the Final Meeting with the
presentation of the result of the project and presentation of
other LIFE projects.
|
E 2
|
30/06/2017
|
30/06/2017
|
DONE
|
CEAM
|
|
D.E.3.1.
After-LIFE communication plan in English and electronic
format
|
E 3
|
30/06/2017
|
30/06/2017
|
DONE
|
CEAM/ALL
|
|